Skip to content

Check List and Period ​

The robot requires regular maintenance to perform in the best condition.
As such, a regular maintenance schedule is highly recommended. During maintenance, the following check list has to be done.
If you encounter an issue during the inspection that you cannot resolve on your own, please contact the manufacturer.

WARNING

  1. During maintenance, cut off the power to the system (Control Box and Robot Arm) and perform work.
  2. For pneumatic/electric line passing models, remove the connected energy source (pneumatic/electric power) and perform the work.

Collaborative Robot Inspection Items and Intervals

Component Inspection Category Inspection Item Inspection Details and Criteria Inspection Interval
Robot Arm Appearance and Hardware Appearance and DamageCheck the robot arm exterior for cracks, structural deformation, and deep scratches.Every 6 months
Bolt Tightness Check the tightness of the bolts on the robot base and base mounting bracket. (Apply alignment marks during installation.)
Check the tightness of the bolts connecting the robot tool flange to the end effector (gripper, etc.).
CleaningCheck that dust, organic solvents, oil mist, and other contaminants have been removed from the robot arm surface.Every month
Cables and Wiring Cables and ConnectorsCheck the cable connecting the robot arm and control box for wear and damaged insulation, and check that the connectors are securely fastened.Every 6 months
Zero Position Check and Accuracy CalibrationMove the robot to its zero position, check the alignment of the joint reference holes, and adjust the encoders.Every 12 months
Control Box Cooling and Environmental Management Fan OperationCheck that the control box fan operates normally.Every 12 months
Fan Filter InspectionCheck the control box fan filter for dust buildup. (Clean or replace as necessary.)
Safety and System System Data BackupBack up robot programs, SET-UP settings, and safety configuration data.Every 6 months
Software UpdateReview and install manufacturer-recommended security patches and the latest firmware version.Every 12 months
Installation Environment Check whether the control box is installed in an enclosed space. (Installation in enclosed spaces is prohibited.) Once after installation
Check whether the intake fan on the left side, when viewed from the front door, faces a wall, and ensure sufficient clearance for unobstructed airflow.
Input Voltage CheckVerify that the input power supply is single-phase 110 or 220 V AC.Once after installation